← All Logsheets
Site Safety Manager / SSC
Daily Inspection Report
NYC Building Code Chapter 33 · BC §3301.9.1 · DOB Required Daily Documentation
PL-001
Project Address
General Contractor Block / Lot
DOB Job No. DOB Permit No.
SSM / SSC Name License No.
Date Shift AM PM Night
Time In Time Out
Weather (AM / PM) No. of Workers on Site
Areas Inspected
Safety Orientation Held Today Yes No Building Reached 75 ft.
Deck Floor Walkable Floor
Stripping Floor Stairway Within 40 ft. of Deck
Contractors & Workers On Site — BC §3301.9
# Company / Subcontractor Workers Scope of Work & Floor / Location
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25

SSM / SSC Daily Inspection Report  (Page 2 of 2)

General Safety — BC §3309 / §3310 / §3315YESNON/A
Weekly contractor coordination meeting conducted and documented
Construction standpipe system tested, pressurized, and log current — BC §3320
Perimeter construction fence inspected, continuous, and compliant — BC §3310.9
Vertical debris netting inspected, properly secured at all attachment points
Horizontal netting installed  (Date: )
Horizontal netting removed  (Date: )
Horizontal netting daily inspection completed and deficiencies corrected
Guardrail systems (42" top rail, 21" mid-rail) and toe boards properly installed — BC §3315.3
All floor openings and penetrations covered, secured, and marked — BC §3315.1
All stairways have compliant handrails and mid-rails; stairway lighting operational
Required DOB, FDNY, OSHA, and site safety signage posted and legible
Public Protection & Site Maint. — BC §3307 / §3309.4YESNON/A
All public sidewalks and pedestrian routes free of tripping and slipping hazards
Guards, shields, and barricades properly separate the public from all construction hazards
Adjacent property protected as required — roof, window, and overhead protection in place
Traffic control flaggers stationed as required by DOT permit conditions
All means of egress and ingress clear and unobstructed; sidewalk shed free of debris
Debris containers provided, covered, and secured; combustible debris removed daily
Materials stored minimum 10 ft. from open floor edges (5 ft. where perimeter < 1,000 SF)
Debris chutes installed and maintained per code; plans and permits on site
Material Handling & Hoisting — BC §3318 / §3319YESNON/A
DOB crane / derrick approval certificate on site; operator license current and available
PE-stamped crane pick schedule on site and reviewed prior to lifting operations
DOT highway / street closing permits available on site and properly posted
Communication system confirmed among all parties during all hoisting operations
Flaggers and exclusion zones in place during all lifting and material hoisting operations
All hoisted loads inspected and properly rigged; rigging equipment in good condition
Logbook, Training & Permits — BC §3321 / LL 196YESNON/A
Sidewalk shed / supported scaffold daily log updated
Suspended scaffold / rigger's daily log updated
Active DOB, DOT, DEP, and FDNY permits posted on site
Approved Site Safety Plan on site; daily spot check conducted
Approved scaffold drawings and permits on site (supported and suspended)
Noise / dust mitigation plans posted and conditions being met
Fall protection equipment inspection log current; PFAS log updated
Safety orientation log updated; new worker orientations completed today
Contractor toolbox talk conducted and recorded this week
SST Cards verified, scanned, and logged per Local Law 196 / 2017 — BC §3321.2
4-hr supported scaffold training verified (all workers accessing supported scaffold)
16-hr suspended scaffold training verified (all workers on suspended scaffold)
32-hr scaffold erection / dismantling training verified (erectors)
Licensed Rigger / Rigging Foreman certificate confirmed on site
Incidents — Report ALL injuries, near-misses, and property damage
Injury / Accident to Worker or Public YesNo Near-Miss Reported YesNo Report Filed YesNo Photos Taken YesNo
Brief Description of Incident
Agency Inspections
Regulatory Inspection Today YesNo Agency Inspector Name / Badge No.
Violation / SWO Issued YesNo SWO Lifted (Date / By)
Shift Safety Personnel
Concrete Safety Manager (CSM) Name License #
Fire Safety Manager (CSFSM) Name COF No.
Licensed Rigger / Rigger Foreman License #
Observations, Conditions & Corrective Actions
SSM / SSC Name (print) License # Signature Date
Alternate SSM / SSC (print) License # Signature Date